South Delta Secondary School (SDSS) Track Project
STAGE: Phase 3
(June 13, 2019)—Over the summer the much-anticipated upgrades to the SDSS Track will be taking place.
PROJECT TIMELINE
June 17 – July 5 Supplementary asphalt repairs
July 7 Site will be fenced and closed to the public till project completion.
July 8 – 10 Material will be staged on site
July 10 – July 17 Preparation and Cleaning of surface
July 17 – August 1 Installation of the Mat track
August 2 – August 8 Line Painting
August 9 Clean up and project completion
This schedule is for information purposes only. Some timeline slippage may result depending on weather conditions.
More information on the project and any updates over the summer
can be found on the Delta Facilities webpage.